Projects

Symal contracted R&B Civil for FRP works on both the Golden Plains and Cressy Terminal Stations projects. These encompassed the construction of footings, slabs, stairs, and culverts for the Transformers, 220kV, and 500kV Switchyards.

Golden Plains Windfarm and Cressy Terminal Stations

Client: Symal

Location: Rokewood, Victoria

Date Completed: Feb 2024

Scope:
FRP of 100+ Transformer Footings
FRP of Transformer Slabs
FRP of Insitu Concrete Stairs
FRP of Culverts

Beon Solar Farm, Melbourne Airport

Client: Symal

Scope:
Installation of in-situ pits
Road crossing slabs
HV Control building slabs

Narre Warren Road Upgrade

Client: Symal

Scope:
Labour hire
Construction of ground beams
Installation of in-situ pits
Traffic island infills
Formwork, Reinforcement, and Pouring (FRP) for shared user paths

Clyde Primary School

Client: Appia Group

Scope:
Site establishment of compounds
Preparation of detailed excavations
Formwork, Reinforcement, and Pouring (FRP) of ground slabs

Wollert Primary School

Client: Appia Group

Scope:
Site establishment of compounds
Preparation of detailed excavations
Formwork, Reinforcement, and Pouring (FRP) of ground slabs

Falls Creek, Cloud Nine Ski Resort

Client: Duggan and Hanlon

Scope:
Installation of Dincel walls
Basement slab construction
Suspended slab installation
Column construction
Retaining walls construction